Côd QR

Resource-Constrained Multi-Project Reactive Scheduling Problem With New Project Arrival

Reactive project scheduling is an important branch of project scheduling under uncertainty. This paper proposes a resource-constrained multi-project reactive scheduling problem (RCMPRSP) with new project arrival to minimize the adjustment cost of the baseline schedule while achieving the determinist...

Disgrifiad llawn

Wedi'i Gadw mewn:
Manylion Llyfryddiaeth
Prif Awduron: Wuliang Peng, Dongmin Yu, Jiali Lin
Fformat: Artigo
Iaith:Inglês
Cyhoeddwyd: IEEE 2023-01-01
Cyfres:IEEE Access
Pynciau:
Mynediad Ar-lein:https://ieeexplore.ieee.org/document/10164087/
Tagiau: Ychwanegu Tag
Dim Tagiau, Byddwch y cyntaf i dagio'r cofnod hwn!