Resource-Constrained Multi-Project Reactive Scheduling Problem With New Project Arrival

Reactive project scheduling is an important branch of project scheduling under uncertainty. This paper proposes a resource-constrained multi-project reactive scheduling problem (RCMPRSP) with new project arrival to minimize the adjustment cost of the baseline schedule while achieving the determinist...