Modeling construction cost overrun risks at the FEED stage for mining projects using PLS-SEM

The mining industry consistently faces significant cost overruns during construction, rooted in the Front-End Engineering Design (FEED) stage, with overruns reported between 25% and 37%, underscoring the need to investigate early-stage risk factors. This study utilizes Partial Least Squares Structur...